Skip to content
Guide · CT Clamps · 3-Phase Supply

CT clamps for single-phase vs 3-phase systems why installers get this wrong on 3-phase supplies

A single-phase inverter only has one CT clamp — so on a 3-phase house it can't see what's happening on the other two phases. The battery sits idle while the kitchen on a different phase runs flat out. This guide explains the four common topologies, why the UK smart meter changes the maths, and which one is the right answer.
  • Independent technical advice
  • No brand affiliation
Wrong-spec inverter on your 3-phase supply?

A remote diagnostic confirms whether your inverter topology is wrong from 7–14 days of monitoring history — usually in 30 minutes. We give you a clear written report to take to your installer.

Book your remote diagnosticHow diagnostics work

Made contact for assistance with my GiveEnergy battery that wasn't discharging. Ronald looked at my issue the same day, identified the root cause with a clear explanation of what was going on along with some options on how to remediate the issue. So far my battery is now working and keeping my fingers crossed that it stays this way. Ronald is a very experienced and knowledgeable engineer and I would recommend.

Al · Jul 2026 Google

My GivEnergy solar and battery system is failing intermittently, GivEnergy is in administration and so is my installer, so it was a relief to get Ron’s expert advice.

Steve Trossell · Jun 2026 Google

The ONLY technical person, who has ever exceeded my own high standards !!!! Being a professional commissioning engineer of over 37yrs in the field of emergency power generation, I approached Ron for some advice on a GivEnergy battery issue as happy to state I don't know everything. Not only did he reply immediately, his advice got the system working and all on a Sunday. You really do not get support as good as this anywhere now for anything. Thank you Ron

Ridgeback Ray · Oct 2026 Trustpilot

Saw Ron was advertising a refurbished 9.5 kWh on Facebook, within a couple of days Ron delivered and installed it into my current system, my existing 9.5 batter was also. Gen 2 running on firmware 3022. Literally took him 30 mins, from start to finished, within a couple of days the two batteries had balanced themselves, it’s now been a week with Predbat in control. Working perfectly , could not recommend Ron more highly Top Man!

Mark Herrington · Nov 2026 Google

When my GivEnergy battery started playing up it became basically useless and several companies I called said they couldn’t help. Solar Tech Support really knew their stuff, communicated very well and resolved the problem quickly. Without them I’d have had to buy a replacement battery.

A D · Jun 2026 Google

Solar Tech Support is an absolute lifesaver. My solar and battery system stopped working completely, but after one quick phone call, they fixed the problem straight away. The original provider, GivEnergy, has gone into administration, leaving me entirely without support from the original installers. It was a terrible situation on GivEnergy’s part, but thankfully, Solar Tech Support came to the rescue!

sohaib maroof · Jul 2026 Google
Background

What a CT clamp does — in one sentence

A CT clamp (current transformer) wraps around a live cable and measures the current flowing through it without breaking the circuit. Your inverter uses its CT data to decide when to charge the battery, when to discharge, and when to push power back to the grid. If the CT misses load, the inverter misses load. Misplace a CT, install the wrong topology for the supply, and the system makes the wrong decisions — every second of every day.

On a single-phase supply the choice is simple: one phase, one CT, one inverter. On a 3-phase supply (most large UK homes, almost all commercial property, and any property with an 11 kW or 22 kW EV charger) the picture splits into four common topologies. Three of them have failure modes that show up only after install, when the homeowner notices the battery emptying while the kitchen on a different phase is running flat out.

The pivotal fact

What your smart meter actually does

UK SMETS2 polyphase smart meters measure import and export per phase, then sum the three phases algebraically before reporting an import register and an export register to your supplier. The export register only ticks up when the whole-house net across all three phases is exporting at that instant. The import register only ticks up when the whole-house net is importing.

Example

L1 exports 2 kW. L2 imports 1 kW. L3 imports 0.5 kW. Net = 0.5 kW of export → SEG register accrues 0.5 kW. Now flip it: L1 exports 2 kW, L2 + L3 import 3 kW total. Net = 1 kW of import → import register accrues 1 kW. The export register doesn't move. One inverter cannot tell what's happening on the other two phases unless its CT setup measures all three.

This is the single most important fact in this guide. Everything below — why topology 1 fails, why topology 2 wastes battery cycles for no SEG credit, why topology 3 works but stresses one phase — derives from how the smart meter sums.

Topology 1

Single-phase inverter on a 3-phase supply (one CT on L1)

The most common wrong-spec install. The inverter only knows what's happening on the phase it's wired to.

L1 L2 L3 Smart meter SMETS2 polyphase Nets L1+L2+L3 Consumer unit House loads Inverter Hybrid + battery CT Kettle Oven EV charge Inverter sees only L1. L2 oven (3 kW) + L3 EV (7 kW) invisible. Battery sits idle while meter imports 10 kW.
Generation / export
Grid import (paying)
Mixed / partial import
CT measurement point

The inverter is wired to L1, neutral, and earth. Its single CT clamps around the L1 incomer at the consumer unit. The inverter sees L1 only — it has no visibility of L2 or L3, no awareness of cross-phase loads, and no ability to inject or absorb current anywhere except L1.

When L2 has the kettle on (3 kW) and L1 is idle, the inverter sits there with a full battery while the meter charges you for 3 kW. When L3 is charging an EV at 7 kW, you import the full 7 kW from the grid — the battery doesn't fire because the inverter doesn't see the load. When L1 has its own load, the inverter does what it's designed to do, but only on a third of the household.

Typical self-consumption on a UK 3-phase domestic supply with this topology is 20–45% of generated kWh, against 75–88% achievable with topology 4. There is no software fix. The fix is to change inverters.

It can also breach DNO rules. A single-phase 5 kW inverter on one phase is 22 A on that phase — above the G98 16-amp-per-phase limit, so the install needs a G99 application that's rarely granted on a 3-phase supply where a balanced product exists. The over-export onto one phase also raises L1 voltage and triggers the inverter's own G99 over-voltage trip sooner than a balanced install would.

Topology 2

Three single-phase inverters, one per phase (three CTs)

Looks balanced on paper, fails on UK net metering.

L1 L2 L3 Smart meter SMETS2 polyphase Nets L1+L2+L3 Consumer unit House loads Inverter 1-ph #1 · L1 Inverter 1-ph #2 · L2 Inverter 1-ph #3 · L3 CT1 CT2 CT3 Each inverter chases its own phase to zero. But the smart meter nets all three. L1 inverter exports while L2 imports → meter cancels them out → no SEG export credit, battery drained for nothing.
Generation / export
Grid import (paying)
Mixed / partial import
CT measurement point

Three single-phase inverters, each with its own DC array or battery, each wired to one phase, each with one CT measuring its own phase. The three inverters operate independently — none of them has any visibility of what the others are doing.

Each inverter tries to zero its own phase. Locally, each phase is balanced. But the smart meter is netting all three phases, and the inverters don't know it.

The failure mode is wasted cycling. L1 inverter exports 2 kW to cover its own zero-target. L2 inverter imports 2 kW from the grid because L2 has a 2 kW load and an empty battery. The meter sees: net zero. You're billed nothing for that instant — but no SEG credit either, and the L1 battery just discharged 2 kW for nothing.

Worse, the cross-phase asymmetry can shift hour to hour. SEG export only registers when the whole-house net is exporting. With three independent inverters chasing per-phase zero, the system will routinely create flows that the meter nets to a wash, paying neither party. Typical self-consumption: 55–70% — better than topology 1, worse than 3 or 4.

It's also the most expensive of the four. Three inverters + three CTs cost roughly 50–100% more than a single 3-phase unit of equivalent total kW. The only times it's the right call: heritage upgrades being done one phase at a time, or where each phase needs its own backup-power island.

Topology 3

Single-phase inverter with a 3-phase energy meter

One inverter, all output on one phase — but it sees all three phases. Works on UK SEG.

L1 L2 L3 Smart meter SMETS2 polyphase Nets L1+L2+L3 Consumer unit House loads 3-phase meter EM24 / ET340 Inverter's view Inverter 1-ph · all on L1 Modbus RS485 Inverter nets total household to zero — but pushes all output onto L1. Works on UK SEG (smart meter nets the same way). Capped by single-phase 16 A rule — G99 above 3.68 kW. Some inverters use 3 internal CT clamps instead of an external meter — functionally identical.
Generation / export
Grid import (paying)
Mixed / partial import
CT measurement point

Electrically the inverter is wired to one phase (typically L1). Instead of a CT clamp it uses an external 3-phase energy meter sitting on the supply tails, reading all three phases and reporting whole-house net via Modbus RS485 back to the inverter.

The inverter's control loop targets total imported power = 0 across the sum of L1+L2+L3. If L2 has 2 kW kettle and L3 has 1 kW load, the inverter pushes 3 kW out onto L1. The smart meter sees L1 = −3 kW, L2 = +2 kW, L3 = +1 kW → net 0. Exactly the behaviour SEG was designed to reward.

Self-consumption matches topology 4 in steady state — typically 70–85%. The catch is what happens when the inverter is exporting hard onto one phase.

A 5 kW inverter exporting at full tilt onto L1 = ~22 A on that phase. That exceeds G98's limit of 16 A per phase, which means the install needs a G99 application. Some DNOs accept this on weak networks; others won't. Below ~3.68 kW it's G98-eligible. Above it, you're applying to the DNO and they may refuse if the local LV network can't tolerate the imbalance.

It's the right answer when a 3-phase inverter isn't available in the desired battery ecosystem, when the inverter capacity stays under 16 A on one phase, and when the DNO accepts the imbalance current. It's the wrong answer when you need more than ~3.68 kW of continuous output and the DNO won't grant G99.

Topology 4

True 3-phase inverter (three CTs or a 3-phase meter)

The default-correct topology. Each phase metered, each phase balanced.

L1 L2 L3 Smart meter SMETS2 polyphase Nets L1+L2+L3 Consumer unit House loads 3-phase meter EM24 / ET340 Inverter's view 3-phase inverter Per-phase balance Modbus RS485 Kettle Oven EV charge Each phase metered + balanced independently. Self-consumption 75–88%. G98-eligible up to 3×16 A (~11 kW total). No imbalance issue. The correct topology for any 3-phase supply.
Generation / export
Grid import (paying)
Mixed / partial import
CT measurement point

The inverter has three independent phase outputs (or a firmware-bonded 3-phase cluster). It can source or sink current on each phase independently. It uses either three CT clamps (one per phase) or an external 3-phase Modbus meter to measure all three phases.

Each phase is balanced to zero against its own load. If L1 has 2 kW load, the inverter supplies 2 kW on L1. If L2 has 1 kW load, it supplies 1 kW on L2. If there's surplus PV after household load, it exports balanced kW across all three phases.

Self-consumption is the highest of the four topologies — typically 75–88% of generated kWh — and the residual loss is just the standard battery-empty edge cases that affect any storage system.

Balanced by design means no P29 voltage-unbalance risk and no G98 imbalance breach. G98-eligible up to 3 × 16 A = ~11 kW total inverter output on a 3-phase service; anything above goes G99.

The premium over single-phase: typically 20–40% on inverter hardware, plus ~£150–250 for the 3-phase meter if it isn't bundled. For any 3-phase supply that's getting more than ~3 kWp of PV or a battery system intended to cover the whole house, the premium pays back inside the system lifetime through self-consumption gains alone — never mind the resilience of getting the topology right first time.

Comparison

Side-by-side comparison

Topology CTs G98 ceiling SEG net works? Self-consumption DNO risk
1 — 1-ph inv, 1 CT 1× on L1 16 A on one phase Partly — meter nets but inverter is blind to it 20–45% Voltage rise on one phase; imbalance
2 — 3× 1-ph inverters 3× (one per inverter) 16 A/phase, balanced Partly — cross-phase waste 55–70% Multiple-G98 acceptance varies by DNO
3 — 1-ph inv + 3-ph meter External 3-phase meter 16 A on host phase Yes — designed for it 70–85% Imbalance current on host phase
4 — True 3-phase inverter 3× CTs or 3-phase meter 3×16 A ≈ 11 kW total Yes — designed for it 75–88% None notable
DNO rules

G98 vs G99 — the rules behind the topology choice

The UK distribution code from ENA (Energy Networks Association) sets two thresholds that decide which paperwork applies:

G98 — Connect and Notify

Up to 16 A per phase. At 230 V that's ~3.68 kW single-phase or ~11 kW total on a balanced 3-phase install. You install first; the DNO is notified within 28 days. No pre-approval.

G99 — Apply and Connect

Anything above 16 A per phase, or any installation with multiple G98 units at one premises that breaks the imbalance rules. You apply to the DNO before commissioning. The DNO can take up to 45 working days to reply on the standard route, or 10 working days on the Fast Track.

The imbalance rule is the part most installers miss. Multiple G98 single-phase units at one premises are only acceptable when the imbalance between phases does not exceed 16 A. Topology 3 (single-phase inverter pushing all output onto L1) is simpler: an inverter rated above 3.68 kW is over 16 A on that phase on its own, so it is G99 even with export limited.

If you want the full picture on the paperwork, see our G98 vs G99 explained guide.

EV charging

EV chargers — the topology stress test

A 3-phase EV charger draws roughly 16 A on each of the three phases (11 kW) or 32 A on each (22 kW). For the single-phase EV-charger CT placement story, see our EV charger CT placement guide. This is where the topology choice shows up most aggressively on the homeowner's bill.

Topology 1

5 kW single-phase inverter covers ~1/3 of the EV load if it happens to share a phase. Solar self-consumption during EV charging: 0–33%.

Topology 3

Inverter pushes 5 kW onto L1 to offset 11 kW total. Meter nets to 6 kW import. Solar covers ~45% of EV load.

Topology 4

9–11 kW 3-phase inverter fully covers an 11 kW EV charge. Solar self-consumption: ~100%.

22 kW charger

No domestic inverter has the capacity. Topology 4 still minimises grid draw the most.

If you're adding an EV charger to a 3-phase house — or planning a new solar install for one — topology 4 is the only choice that makes the numbers work.

Industry context

Why most installers default to single-phase even on 3-phase supplies

It isn't usually malice — it's friction. The reasons are mundane and they stack up:

Stock and training

The van carries single-phase hybrids. They don't normally stock 3-phase units.

Cost

20–40% inverter premium, plus a 3-phase meter at £150–250, plus more complex CT routing.

Battery ecosystem

Several popular UK battery stacks were single-phase-only until recently. The installer wants the chemistry they know.

Commissioning

Single-phase + one CT can be commissioned by one electrician in half a day. 3-phase needs phase-rotation checks and balanced-output verification.

DNO paperwork

G98 single-phase notify is 28 days post-install. G99 usually needs approval first: up to 45 working days on the standard route, 10 on the Fast Track. Installers under quota pressure choose the path that ships fastest.

None of these reasons survive contact with the homeowner's actual bills, but they explain why so many 3-phase supplies end up with the wrong topology in the first place.

Pre-install audit

What to ask your installer (or your existing installer)

Before commissioning, or as a post-install audit:

01
Is my supply single-phase or 3-phase?

If you don't know, check your meter. Three meter tails coming in (excluding neutral and earth) = 3-phase.

02
Is the inverter single-phase or 3-phase?

Read the model number off the inverter itself. “1P”, “1-phase”, or “single-phase” in the datasheet means it generates on one phase only — regardless of how many CTs it accepts.

03
How many CT clamps are fitted, and on which phases?

One CT on a 3-phase supply = topology 1, and you need to know that going in.

04
What does the inverter chase to zero — one phase or the whole house?

If the installer can't answer this, the chances are it's topology 1.

05
Was a G99 application filed?

If the inverter is over 3.68 kW on one phase and there's no G99 reference, the install may not be DNO-compliant.

DIY diagnostic

How to spot you've got the wrong topology — without opening the inverter

The fastest diagnostic without lifting a panel:

01

Run a known load on a phase that's not the inverter's phase — e.g. plug a 2 kW heater into a socket you know is on a different phase circuit.

02

Watch the inverter monitoring app. If the battery doesn't respond and the grid import jumps by 2 kW, the inverter can't see that phase. Topology 1 confirmed.

03

Cross-reference with the smart-meter in-home-display (IHD) reading. If the IHD reports by 2 kW of import while the inverter says “self-consumed”, the inverter is operating on bad data.

A remote diagnostic from us pulls 7–14 days of monitoring history and looks at the cross-phase pattern automatically — usually catches a wrong-topology install inside the first 30 minutes. For the wider “CT clamp installed wrong” symptom set (reversed readings, battery not charging, monitoring inverted), see CT clamp installed wrong.

FAQ

Frequently asked questions

It will operate but only on the phase it's wired to. Loads on the other two phases are invisible to it. Typical self-consumption drops from 75–88% (with a 3-phase inverter) to 20–45%. An inverter rated above 3.68 kW is also over G98's 16 A per phase limit, so even with export limited it needs a G99 application.
SMETS2 polyphase smart meters measure each phase separately, then sum them algebraically before reporting an import register and an export register to your supplier. The export register only ticks when the whole-house net across all three phases is exporting. This is why topology 2 (three single-phase inverters) wastes cycles — phase-A export gets cancelled by phase-B import at the meter, with no SEG credit either side.
It's an external meter clamped around all three phase tails at the supply incomer, communicating with the inverter via Modbus RS485. The inverter uses it instead of (or in addition to) CT clamps to net total household import to zero. Common 3-phase meters in the UK channel include the Carlo Gavazzi EM24, ET340, and EM340, and similar Eastron units. Several single-phase inverter ranges support this mode for net metering across phases.
You can, but it usually performs worse than a single 3-phase inverter and costs more. Each inverter chases its own phase to zero. The smart meter nets all three. So when phase A exports while phase B imports, the meter cancels them — no SEG credit and a battery cycle wasted. Typical self-consumption: 55–70%, vs 75–88% for one true 3-phase unit.
Run a known load (e.g. a 2 kW heater) on a phase that's not your inverter's phase. Watch the inverter app and your smart-meter in-home-display. If the IHD jumps by 2 kW of import while the inverter shows no response, it's topology 1 — single-phase inverter, one CT, blind to the other phases. A 30-minute remote diagnostic from us pulls 7–14 days of monitoring and catches the pattern automatically.
A true 3-phase inverter (topology 4), sized at 9 kW or above, ideally with a 3-phase battery system. The EV draws ~16 A on each of the three phases. Only a 3-phase inverter can offset all three. A single-phase inverter on one phase (even with a 3-phase meter) caps at ~3.68 kW and can only offset roughly a third of the EV load. The maths only works for topology 4.
A remote diagnostic from us is free, no fix no fee. We pull 7–14 days of your inverter monitoring data and cross-reference it with smart-meter readings to confirm whether the topology is wrong, what's installed, and what would need to change. If the data turns out to show no diagnosable issue, you don't pay. See the remote diagnostic service for the full scope.
Most 3-phase topology diagnoses are done inside a single 30-minute session. You book a slot, share your monitoring login (or screenshots) and your smart-meter half-hour data if you have it, and we work through the cross-phase pattern. The written engineer report — clear enough to take to your installer or your DNO — is usually returned the same day.

Think your installer fitted the wrong inverter for your 3-phase supply?

A remote diagnostic confirms the topology from monitoring data and gives you a written engineer report — clear enough to take to your installer or to a DNO. £125, no fix no fee.

By submitting you agree to be contacted about your diagnostic request. We don't share your data with 3rd parties.

Call 07944 877 329 Book free diagnostic