Contacted Solar Tech Support when trying to understand what my Givenergy inverter problem might be and what might be my options. Received good/honest advise which backed up my thoughts.
DNO export application support G98 and G99 paperwork handled for you
- All five UK DNOs — UKPN, NGED, NPg, SPEN, SSEN
- G98 notification or G99 approval — we determine which you need
- Retrospective filing if installer never registered the system
- Confirmation reference number provided on completion
We prepare and submit your G98/G99 export application end to end — paperwork, technical schedules, and DNO liaison — so you can export and get paid for what you generate.
Start DNO ApplicationI've spoken to Ron a couple of times with issues with my Givenergy installation. Such a friendly knowledge guy very highly recommended. Thank you very much for resolving my issues
Excellent response to diagnose a problem on our SolarEdge installation. Kept us informed at every step. Diagnosis quickly completed and solution implemented.
I reached on behalf of a friend, who had lost control of their battery following a storm. A couple giv energy “dealers” had attempted and said different fixes. None worked. Solar tech support solved it remotely on the first attempt almost instantly. Genuinely a 10/10 service.
Contacted Ron with a problem and he sorted it out quickly with no problems at all. Very knowledgeable on anything solar/ batteries. I would recommend him to anyone
Our SolarEdge PV system with LG batteries had its first hiccup after 8 years of hard work. The Inverter failed. Fortunately I found Solar-Tech-Support who diagnosed the problem very quickly, ordered a replacement unit and fitted it shortly after we received the unit from SolarEdge. Very thorough and professional approach. Thank you, a solid 5 star recommendation.
What's included
G98/G99 Assessment
We review your inverter specifications and system configuration to determine whether G98 or G99 applies. The threshold is 3.68 kW per phase of inverter output — not panel capacity, not battery size. We confirm the correct route before filing anything.
Application Preparation
Each DNO has its own portal and form requirements. We prepare the full application with your system specifications, MPAN, site address, and supporting documentation formatted to match the specific DNO's requirements.
Submission & Tracking
We submit the application directly via the correct DNO portal, track it through to acceptance, and provide you with the confirmation reference number. For G99, we follow up throughout the approval window.
Export Limit Configuration
If the DNO approval includes conditions — an export limit, reactive power setting, or other parameter — we can configure these in your inverter remotely, ensuring your system complies with the approval letter from day one.
Ideal for
How it works
We assess your system and determine the correct application
G98 or G99 is determined by your inverter's maximum export capacity — not your panel output, not your battery size. The single-phase threshold is 3.68 kW. We review your inverter model and system configuration to confirm which standard applies and whether Fast Track G99 is available. If your system is already installed but unregistered, we determine whether a retrospective G98 notification or a retrospective G99 application is needed.
Application prepared with correct documentation
Each of the five UK DNOs has its own portal, forms, and documentation requirements. We prepare the full application package: system specifications, inverter model and serial number, total generation capacity, export capacity, MPAN, site address, and installation date. Everything formatted to match the specific DNO's requirements so nothing is sent back for correction.
Submitted and tracked through to confirmation
We submit the application via the correct DNO connections portal. For G98, this is a notification — no approval wait. For Fast Track G99, the DNO has 20 business days to respond; if they don't object, the connection is deemed approved. For standard G99, the window extends to 65 business days. We track the application and follow up with the DNO if needed until you have a confirmed registration reference number.
Export limit and conditions configured
G99 approvals often include conditions — a specific export limit, reactive power requirements, or communication settings. If your approval letter includes conditions, we can configure these in your inverter remotely so your system complies from day one. We also verify that your existing export limit settings match the DNO agreement, which is a common source of problems after smart meter installations.
G98 vs G99 — quick reference
The correct standard depends on your inverter's maximum export power, not your panel capacity or battery storage. Here's how the two standards compare. For a full breakdown, see our complete G98 vs G99 guide.
Post-installation notification only — no prior approval needed.
Submitted to your DNO after the system is installed and commissioned.
No waiting period. System can export immediately once notification is filed.
Applies to most standard single hybrid inverters (e.g. GivEnergy Hybrid 3.6 Gen 3, SolarEdge 3.68 kW).
Formal application required — must be approved before installation begins.
Fast Track G99: DNO responds within 20 business days (~4 weeks).
Standard G99: DNO responds within 65 business days (~13 weeks).
Applies to larger hybrid inverters (e.g. GivEnergy Hybrid 5.0/8.0 Gen 3, Sunsynk 5 kW+).
Common misconception: G98 and G99 are determined by inverter output power, not battery storage capacity. You can have 47.5 kWh of battery storage and still fall under G98 if your inverter is rated at 3.68 kW or below. Conversely, a system with no battery at all but a 5 kW inverter requires G99. See our full guide for details.
Not sure which applies to your system? We determine the correct standard as part of the service — just tell us your inverter brand and model when you book.
When you need DNO application support
DNO registration is a legal requirement for any grid-connected generation system in the UK. These are the most common situations where our support is needed.
Installer never filed the paperwork
The most common issue. The installer commissioned the system but never submitted the G98/G99 notification. This can block SEG payments, cause problems during property sales, and technically means your system is non-compliant. We file retrospectively. See also: DNO paperwork recovery guide.
System upgrade changes export capacity
Upgrading from a 3.6 kW to a 5 kW inverter, or adding a second inverter, may push your export capacity above the G98 threshold into G99 territory. A new or amended application is required before the upgrade is commissioned. We handle the variation and new submission.
SEG application rejected
Energy suppliers require confirmed DNO registration before accepting a Smart Export Guarantee application. If your SEG was rejected due to missing registration, we file the DNO application, obtain confirmation, and you can resubmit with the reference number.
Bought a house with existing solar
You've moved into a property with solar panels and the previous owner's documentation is incomplete or missing. We check DNO registration status, file retrospectively if needed, and ensure the registration reflects the current ownership.
Constrained network area
Some DNOs require G99 even for systems below the 3.68 kW threshold if your area has reached cumulative generation capacity limits. We check your area status with the DNO and handle the G99 submission if required, including any export limitation conditions.
Export limit issues after smart meter
Smart meter installations can disrupt export limit settings, sometimes capping export to 0 kW. We verify your inverter's export settings match the DNO agreement and correct any mismatches. If the DNO agreement itself needs updating, we handle the variation. See also: export limitation guide.
Frequently asked
Need DNO paperwork sorted?
Whether it's a new G98 notification, a G99 application, or retrospective filing for a system that was never registered — we handle the entire process. From £45.
- G98 notification or G99 approval — we determine which
- All five UK DNOs covered
- Retrospective filings for unregistered systems
We use cookies to measure traffic and improve our ads — including sharing limited, hashed details with Meta (Facebook) to measure ad performance. Accept, or decline for essential cookies only. Privacy policy
Got a solar fault or need a quick answer? Drop us a message — we usually reply within a few minutes. Mon–Fri, 9am–7pm.